Construction Update April 2018

Favourable weather conditions at Westbrook in recent months have allowed our civil contractors to make good progress.

In the estate’s southern precinct, Stages 18, 20, 23, 24, 30 and 34 are currently in the final construction phase with titles expected in mid 2018.  Footpath and topsoiling works are being completed and our teams are carrying out mandatory electrical audits and following up with the relevant authorities for compliances.

Similarly, construction on Stages 25, 26 and 27 is progressing well, with titles expected in the final quarter of the year.

As these stages reach completion, our production program is on track for a May 2018 start on Stages 22, 28 and 33.

Our civil contractor will commence duplication works on Leakes Road mid year to complete an infrastructure project that will result in vastly improved access to Westbrook. Landscaping works on our two parks and waterways continue to progress well with the parks to be completed and open to the public in mid 2018.

Turning to Westbrook’s northern precinct, Stages 35, 36 and 38 are in the early stages of construction with earthworks, drainage and sewer works underway.  We remain on track for titles on Stages 35 and 36 at the end of this year and early next year for Stage 38. 

Stages 37 and 39 are now locked in for a May 2018 start with Stages 40, 41 and 42 to follow soon thereafter.

We have been informed by the neighbouring developer that the Doherty’s Road upgrade is in its final stages and will be finalised by the middle of 2018.


Stage 34: Looking South along Hornsby Crescent


Stage 30: Looking West along Quality Street


Stage 18: Looking West along Pendulum Street


Stage 20: Looking East along Lumbrook Parade


Stage 23: Looking East along Migdale Road


Stage 24: Looking South along Europe Street


Stage 25: Looking South along Lumbrook Lane


Stage 26: Looking East along Donahue Street


Stage 35 & 36: Sewer reticulation and drainage works currently underway.