Construction is continuing at a cracking pace at Westbrook as our civil contractor advances work on multiple stages across the estate.

In the Southern Precinct, our Central Park and the Stage 2 Reserve are on track for completion in mid-2018. Landscaping works associated with the Forsyth Road Drainage Reserve and Skeleton Creek Water Quality Asset have commenced with a completion expected in the third quarter of 2018.

Streetscape works have commenced with street trees planted in numerous stages, with nature strips works anticipated to commence in the cooler months of 2018. 

Civil works are in progress for Stages 18, 20, 23, 24, 25, 26, 27, 30 and 34.  Stages 18, 20, 23, 24, 30 and 34 remain on track to settle prior to 30 June 2018, whilst Stages 25, 26 and 27 are expected to settle in the third quarter of 2018.

Civil works have commenced on Stages 35, 36 and 38 in the Northern Precinct, with Stages 37, 39, 40, 41 to commence in the coming weeks.