Construction Update - October 2017

With over 350 lots settled. Construction is over 50% complete in the southern precinct and our first residents have moved in.

 

 

 

 

 

 

 

 

 

 

 

 

Stage 1: Certificates of titles are registered. Public space (Reserve 1) has been granted Council approval and is due to commence construction in late 2017.

 

Stage 2: Certificates of titles are registered. Public space (Reserve 2) has been granted Council approval and is due to commence construction in late 2017.

 

Stage 3: Certificate of titles are now registered

 

Stage 4: Certificate of titles are now registered.

 

Stage 5: Certificate of titles are now registered

 

Stage 6:  Certificate of titles are now registered.

 

Stage 7: Civil Construction is nearing completion. Certificates of titles are anticipated in November 2017.

 

Stage 8:  Certificate of titles are now registered.

 

Stage 9: Certificate of titles are now registered.

 

Stage 10. Certificate of titles are now registered.

 

Stage 11: Certificates of titles are now registered.

 

Stage 12: Certificates of titles are now registered.

 

Stage 13: Certificates of titles are now registered.

 

Stage 14: Certificates of titles are now registered.

 

Stage 15 Certificates of titles are now registered

 

Stage 16: Civil Construction is nearing completion. Certificates of titles are anticipated in November 2017.

 

Stage 17: Civil Construction is nearing completion. Certificates of titles are anticipated in November 2017.

 

Stage 18: Civil Construction has commenced.

 

Stage 19: Civil Construction is well underway. Certificates of titles are anticipated in late 2017.

 

Stage 20: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018.

 

Stage 21: Civil Construction is well underway. Certificates of titles are anticipated in late 2017.

 

Stage 23: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018

 

Stage 24: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018

 

Stage 25: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018

 

Stage 26: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018

 

Stage 27: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018

 

Stage 29: Civil Construction is nearing completion. Certificates of titles are anticipated in November 2017.

 

Stage 30: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018

 

Stage 34: Civil Construction has commenced. Certificates of titles are anticipated in mid-2018