Construction Update - March 2018

Construction is continuing at a cracking pace at Westbrook as our civil contractor advances work on multiple stages across the estate.

In the Southern Precinct, our Central Park and the Stage 2 Reserve are on track for completion in mid-2018. Landscaping works associated with the Forsyth Road Drainage Reserve and Skeleton Creek Water Quality Asset have commenced with a completion expected in the third quarter of 2018.

Construction Update - October 2017

With over 350 lots settled. Construction is over 50% complete in the southern precinct and our first residents have moved in.