North Updates

The North

We are pleased to advise that the Westbrook Northern precinct is now accessible to the public with Stages 35-41 having registered recently.

  • Stages 42, 52, 53, 54 & 56 are well progressed with road base works now complete and kerb & channel works currently underway. These stages are expected to title towards the end of the year.   
  • Stage 43 was awarded to the civil contractor in July 2019. Stripping and bulk earthworks are now complete with sewer reticulation and drainage works currently underway. This stage is expected to title in mid 2020.
  • The landscape construction of Stage 35 Park is programmed to commence in the second half of 2019 and is expected to be completed by third quarter of 2020.
  • The landscape construction of Stage 37 Wetland is programmed to commence in the second half of 2019  and is expected to be completed by mid 2020.
  • The landscape construction and planting of Forsyth Waterway is programmed to commence in the second half of 2019 and is expected to be completed by mid 2020.